We have newly Implemented PS module for our Capital investment Project, previous to this we were using Internal order (statistical) for project related CAPEX to manage budget controlling and Cost center for Expenses now after implementing PS requirement is to transfer all the consumed and committed values for the running project from internal order to WBS.

 

Please suggest - if we transfer internal order cost to WBS then while doing settlement to AUC it will load double/excess value because our current AUC asset has value with Internal order.

 

 

Please suggest how to manage it.

 

 