Dear Team,
I am doing Overall Budget for my Project WBS and availability control is set to Active during Overall Budget Release in configuration. Below are setting for same.
We had configured the tolerance limit as follows.
But, When I am Creating Budget in CJ30 and release the same CJ32, availability control is not triggering automatically as configure.
To activate same I need to manually run CJBN.
Can advise me on how to fix this issue?
regards
Atul Rajmane